Have Your Say

Main Street Huonville Car Park Redevelopment

Inform

The Huonville Main Street Car Park redevelopment is required due to the increasing demand in the Huonville shopping precinct and the need to provide appropriate off street parking for varying user types including mini buses, cars, caravans and recreational vehicles.

In designing the facility the following elements were considered:

  • Current Australia Standards.
  • The need for additional car spaces including accessible parking, loading zones, dedicated long wheelbase vehicle parking, bicycle parking, motorcycle parking and Electric Vehicle charging points.
  • Improved pedestrian safety with dedicated footpaths and lighting.
  • Landscaping and bio-retention gardens.
  • Consultation with key stakeholders.
  • Funding available under the State Government Capital Works Accelerated Loan Project and Council’s Asset Renewal Program.

The Huonville Car Park redevelopment will deliver an increase to the total parking capacity from 89 to 136 spaces which will enable improved access for long wheelbase vehicles, bicycle and motorcycle parking and Electric Vehicle facilities.

The provision of footpaths and lighting will provide safer pedestrian access to the carpark.

A copy of the plans can be found here.

 

STATUS UPDATE JUNE 2019:

All works on this project are now complete.

STATUS UPDATE MARCH 2019:

Stage 1 is progressing well and will be completed by the end of this week (8 March).

Stage 2 will commence on Tuesday 12 March and is expected to take four weeks. While this is under construction the existing carpark and laneway between Huon Arcade and Salamanca Fresh will be closed.

Access to the new carpark (Stage 1) will be via entry/exit Bennett’s Service Station.

A copy of the plan identifying the are affected is located here.

STATUS UPDATE FEBRUARY 2019:

Stage 1 will be completed in the next 3 weeks and will see the sealing of the new carpark, line marking and garden beds installed.

Stage 2 will see work commence on access points to the newly constructed parking area (Stage 1). This will require the closure of the existing carpark and laneway between the Huon Arcade and Salamanca Fresh.

A new footpath has been constructed alongside Salamanca Fresh and will provide pedestrian access to Main Street and the rear parking area, during the construction of Stage 2. Temporary vehicle access to the new carpark will be via entry/exit Bennett’s Service Station.

During Stage 2 construction there may be times when some parking will be restricted for installation of lighting.

A copy of the plan identifying the are affected is located here.